5.5 Installation of Belt Conveyor,Balance Weight,Anchorage Locker
5.5.1 Cantilever supports should be installed after being assembled on the ground.
5.5.2 Cantilever supports shall be supported by using the temporary support,and the temporary support shall have sufficient bearing capacity and can be height-adjustable.
5.5.3 During assembly,the cantilever supports shall be positioned by using the ordinary bolts,and after the relative positions and straightness of two sections of cantilever supports are adjusted to meet requirements,the cantilever supports are connected by using high-strength bolts.
5.5.4 Bucket wheel body should be assembled on the ground,and then,hoisted integrally.
5.5.5 The tail car belt conveyor frame should be assembled on the ground,and then,subjected to segmental hoisting.
5.5.6 The installation of balance weight and balance experiments shall meet the requirements of design and equipment technical documents.
5.5.7 The assembly of cantilever belt conveyor frame shall be in compliance with the following requirements:
1 The center line is adjusted,and allowable deviation shall be 3.0mm;
2 Altitude difference of lower surface at the connection point is adjusted,and allowable deviation shall be 5.0mm.
5.5.8 The installation of cantilever belt conveyor frame shall be in compliance with the following requirements:
1 The center line is adjusted,and allowable deviation shall be 10.0mm;
2 The elevation is adjusted,and allowable deviation shall be±10.0mm.
5.5.9 The assembly of tail car belt conveyor frame shall be in compliance with the following requirements:
1 The center line is adjusted,and allowable deviation shall be 3.0mm;
2 Altitude difference of lower surface at the connection point is adjusted,and allowable deviation shall be 3.0mm.
5.5.10 The installation of tail car belt conveyor frame shall be in compliance with the following requirements:
1 The center line is adjusted,and allowable deviation shall be 5.0mm;
2 The perpendicularity of the support in the middle is adjusted,and allowable deviation shall be 1/1000 of the height of the support.
5.5.11 The installation of anchoring locker shall be based on the rail center line,and shall be in compliance with the following requirements:
1 Parallelism is adjusted,and allowable deviation shall be 3.0mm;
2 Perpendicularity is adjusted,and allowable deviation shall be 3.0mm.
- GB50551-2010球團機械設備安裝工程質量驗收規(guī)范(英文版)
- 電動汽車工程手冊(第六卷):智能網聯(lián)
- GB/T 50770-2013 石油化工安全儀表系統(tǒng)設計規(guī)范(英文版)
- GB/T50609-2010石油化工工廠信息系統(tǒng)設計規(guī)范(英文版)
- DL/T5161.5-2002電氣裝置安裝工程質量檢驗及評定規(guī)程第5部分:電纜線路施工質量檢驗(英文版)
- GB/T 51132-2015 工業(yè)有色金屬管道工程施工及質量驗收規(guī)范
- GB50629-2010板帶軋鋼工藝設計規(guī)范(英文版)
- GB 51156-2015 液化天然氣接收站工程設計規(guī)范
- DL/T 5543-2018 特高壓輸變電工程環(huán)境影響評價內容深度規(guī)定
- DL/T 5493-2014 電力工程基樁檢測技術規(guī)程
- GB/T 50451-2017 煤礦井下排水泵站及排水管路設計規(guī)范
- DL/T5161.17-2002電氣裝置安裝工程質量檢驗及評定規(guī)程第17部分:電氣照明裝置施工質量檢驗(英文版)
- GB/T 50466-2018 煤炭工業(yè)供暖通風與空氣調節(jié)設計標準
- DL/T 5224-2014 高壓直流輸電大地返回系統(tǒng)設計技術規(guī)程
- GB 51044-2014 煤礦采空區(qū)巖土工程勘察規(guī)范(2017年版)