4 Preparation for Submarine Cable Installation
4.0.1 Submarine cable installation permits shall be obtained before installation works commence.
4.0.2 Before marine installation,foreign flag vessels shall obtain the non-open waters entry approvals.
4.0.3 Beach manhole construction shall be completed before cable landing.Beach manholes shall have a grounding device whose earth resistance shall not be greater than 10Ω.
4.0.4 Pre-lay grapnel run and clearance of submarine cable routes shall be carried out in accordance with the requirements of the project contract and design document.
推薦閱讀
- GB50526-2010公共廣播系統工程技術規范(英文版)
- GB 50227-2017 并聯電容器裝置設計規范
- GB 51185-2016 煤炭工業礦井抗震設計規范
- YD/T 5131-2005 移動通信工程鋼塔桅結構設計規范(英文版)
- GB 51138-2015 尿素造粒塔工程施工及質量驗收規范
- GB 51179-2016 煤礦井下煤炭運輸設計規范
- DL/T5161.6-2002電氣裝置安裝工程質量檢驗及評定規程第6部分:接地裝置施工質量檢驗(英文版)
- SH3011-2011石油化工工藝裝置布置設計規范(英文版)
- GB/T 50643-2018 橡膠工廠職業安全衛生設計標準
- GB 51214-2017 煤炭工業露天礦邊坡工程監測規范
- 機械基礎地基動力特性測試規程
- DL/T5161.8-2002電氣裝置安裝工程質量檢驗及評定規程第8部分:盤、柜及二次回路接線施工質量檢驗(英文版)
- GB51105-2015擠壓鋼管工程設備安裝與驗收規范(英文版)
- GB50679-2011煉鐵機械設備安裝規范(英文版)
- NB/T 25046-2015 核電廠水工設計規范