3 Material Inspection and Storage
3.1 General Requirements
3.1.1 The material shall be inspected when delivered to the construction site.The variety,specification,performance of materials shall meet the national product standards and design requirements.The quality of imported materials shall meet the design requirements and contract stipulations.
3.1.2 When there are low temperature impact toughness requirements for materials in the design document,the low temperature impact toughness value in the product's quality proof document shall meet the requirements of the design document.
3.1.3 The materials shall not be used if one of the following conditions exists:
1 The characteristic data of quality proof document disaccord with that of the product standard or technical conditions for procurement.
2 There is disagreement on the characteristic data of the quality proof document.
3 The material object mark does not conform with that in the quality proof document.
4 The materials with reinspection requirements undergo no reinspection or fail in the reinspection.
3.1.4 The place for storing materials shall be smooth without accumulated water and the road shall be unblocked.The mark of materials shall be clear and accurate and the underlying shall be reasonable.The parts packed in boxes and the standard fasteners used for connection should be stored indoors.
- GB50168-2006電氣裝置安裝工程電纜線路施工及驗收規范(英文版)
- DL/T5161.2-2002電氣裝置安裝工程質量檢驗及評定規程第2部分:高壓電器施工質量檢驗(英文版)
- GB 51326-2018 鈦冶煉廠工藝設計標準
- GB 51156-2015 液化天然氣接收站工程設計規范
- 冶金石灰焙燒工程設計標準
- GB/T 51218-2017 機械工業工程設計基本術語標準
- 電力系統無功補償及調壓設計技術導則
- DL/T 5493-2014 電力工程基樁檢測技術規程
- GB 50311-2016 綜合布線系統工程設計規范
- GB/T 51280-2018 工程泥沙設計標準
- GB50078-2008煙囪工程施工及驗收規范(英文版)
- DL/T5161.13-2002電氣裝置安裝工程質量檢驗及評定規程第13部分:電力變流設備施工質量檢驗(英文版)
- GB/T 51172-2016 在役油氣管道工程檢測技術規范
- GB/T 51246-2017 石油化工液體物料鐵路裝卸車設施設計規范
- 中國電池工業年鑒2018-2019