4 Surveying and ROW Clearance
4.1 General Provision
4.1.1 Prior to construction,stake handover work shall be conducted.The contents of stake handover work shall include line control stake,temporary and permanent bench mark provided along the line.Stake handover record shall be signed for approval by representative of each party.
4.1.2 Obstructions shall be located accurately before surveying.Corresponding measures shall be taken to avoid obstructions during construction.
4.1.3 Survey personnel shall position the pipeline centerline and right-of-way limits.Each coordinate of pile shall be rechecked.
4.1.4 Construction contractor check and supervision unit repetition survey method shall be used for construction survey.
4.1.5 The allowable deviation of construction survey shall be compliance with Current national standard requirements of-“Code for Engineering Surveying”GB 50026.
4.1.6 After completion of pipeline erection,as-built survey shall be conducted.The actual survey value shall be indicated on original design drawings.The pipeline as-built drawing and single line diagram shall be drawn up.
4.1.7 After backfilling of pipe trench,the coordination controlling pile,and turning pile shall be recovered to original position.
- 架空輸電線路荷載規范
- GB50460-2015 油氣輸送管道跨越工程施工規范
- GB50170-2006電氣裝置安裝工程旋轉電機施工及驗收規范(英文版)
- GB 51180-2016 煤礦采空區建(構)筑物地基處理技術規范
- 海上風力發電場勘測標準
- GB 51138-2015 尿素造粒塔工程施工及質量驗收規范
- GB/T50663-2011核電廠工程水文技術規范(英文版)
- GB/T 50491-2018 鐵礦球團工程設計標準
- GB 50084-2017 自動噴水滅火系統設計規范
- 錦綸工廠設計標準
- DL/T 5156.1-2015 電力工程勘測制圖標準 第1部分:測量
- GB 51284-2018 煙氣脫硫工藝設計規范
- GB50468-2008焊管工藝設計規范(英文版)
- DL 5068-2014 發電廠化學設計規范
- DL/T5233-2010±800kV及以下直流換流站電氣裝置施工質量檢驗及評定規程(英文版)