4 Surveying and ROW Clearance
4.1 General Provision
4.1.1 Prior to construction,stake handover work shall be conducted.The contents of stake handover work shall include line control stake,temporary and permanent bench mark provided along the line.Stake handover record shall be signed for approval by representative of each party.
4.1.2 Obstructions shall be located accurately before surveying.Corresponding measures shall be taken to avoid obstructions during construction.
4.1.3 Survey personnel shall position the pipeline centerline and right-of-way limits.Each coordinate of pile shall be rechecked.
4.1.4 Construction contractor check and supervision unit repetition survey method shall be used for construction survey.
4.1.5 The allowable deviation of construction survey shall be compliance with Current national standard requirements of-“Code for Engineering Surveying”GB 50026.
4.1.6 After completion of pipeline erection,as-built survey shall be conducted.The actual survey value shall be indicated on original design drawings.The pipeline as-built drawing and single line diagram shall be drawn up.
4.1.7 After backfilling of pipe trench,the coordination controlling pile,and turning pile shall be recovered to original position.
- GB 50260-2013 電力設施抗震設計規范(英文版)
- 設計系統發展研究
- 健康座椅
- GB50168-2006電氣裝置安裝工程電纜線路施工及驗收規范(英文版)
- DL/T5161.2-2002電氣裝置安裝工程質量檢驗及評定規程第2部分:高壓電器施工質量檢驗(英文版)
- GB 51138-2015 尿素造粒塔工程施工及質量驗收規范
- GB 50469-2016 橡膠工廠環境保護設計規范
- 核電站鋼板混凝土結構技術標準
- DL/T 5221-2016 城市電力電纜線路設計技術規定
- GB50580-2010連鑄工程設計規范(英文版)
- 水泥工廠環境保護設施設計標準
- GB50629-2010板帶軋鋼工藝設計規范(英文版)
- 智能家電軟件功能安全標準解析與實踐
- GB 50311-2016 綜合布線系統工程設計規范
- DL/T5161.12-2002電氣裝置安裝工程質量檢驗及評定規程第12部分:低壓電器施工質量檢驗(英文版)