6 Stringing
6.0.1 Prior to stringing,grading for out-of-roundness of pipe ends and wall thickness shall be conducted and stringing works shall be compliance with design requirements.
6.0.2 The landform and geological conditions of right-of-way of pipes intended shall be familiarized and pipes shall be strung on the wider sides when surrounding area is gully,road and bank,etc.Pipes shall not be laid on the structures.
6.0.3 The end-to-tail connection of pipeline is required and neighboring pipe ending turns up to be zigzag shaped and separated.Sand bag or other flexible material should be used for pipe supports.
6.0.4 During stringing,steel pipe shall be stably placed.
6.0.5 For stringing in trench,the safety distance from edge of pipeline to edge of pipe trench shall be in compliance with the provisions of table 6.0.5.
Table 6.0.5 Safety Distance from Edge of Pipeline to Edge of Pipe Trenchy(m)

- DL/T 5044-2014 電力工程直流電源系統設計技術規程
- YS/T 5225-2016土工試驗規程
- 電力調度數據網絡工程設計規程
- GB50542-2009石油化工廠區管線綜合技術規范(英文版)
- GB 51179-2016 煤礦井下煤炭運輸設計規范
- GB 50471-2018 煤礦瓦斯抽采工程設計標準
- GB/T 50761-2018 石油化工鋼制設備抗震設計標準
- GB50629-2010板帶軋鋼工藝設計規范(英文版)
- 換流站接地極設計文件內容深度規定
- GB 51133-2015 醫藥工業環境保護設計規范
- DL/T5231-2010±800kV及以下直流輸電接地極施工及驗收規程(英文版)
- GB50071-2014小型水力發電站設計規范(英文版)
- GB 50360-2016 水煤漿工程設計規范
- DL 5068-2014 發電廠化學設計規范
- GB 51171-2016 通信線路工程驗收規范