3 Mobilization of Equipment and Materials
3.1 Equipment Mobilization
3.1.1 As for equipment mobilization,it is required to prepare the plan for equipment mobilization and orderly organize the mobilization.
3.1.2 The equipment shall be subject to open package inspection and meet the following requirements:
1 Under the organization of the owner,consultant company,manufacturer(or supplier)and construction contractor shall participate in the open package inspection.
2 The site for open package inspection shall be clean and protected against rain and dust.
3 The equipment shall be counted according to the packing list,with their models and specifications checked according to design technical documents.
4 The surface of equipment shall be checked and free of defects,deformation or rust.The exposed oil and gas outlets shall be sealed and protected.The pressure indicator for the tank with inflation protection shall indicate positive pressure.
5 The equipment shall be accompanied with the quality qualification document,while the imported equipment shall be provided with the commodity inspection certificate.
6 It is required to count and register the documentation attached with the packing,spare parts and special tools.
7 It is required to record the open package inspection results and handle the procedures for equipment hand-over.
- GB/T 50537-2017 油氣田工程測量標準
- GB/T 51338-2018 分布式電源并網工程調試與驗收標準
- 配用電通信技術及產業發展報告
- 加油站在役油罐防滲漏改造工程技術標準
- GB50588-2017水泥工廠余熱發電設計標準(英文版)
- GB50169-2006電氣裝置安裝工程接地裝置施工及驗收規范(英文版)
- GB50542-2009石油化工廠區管線綜合技術規范(英文版)
- GB/T 50934-2013 石油化工工程防滲技術規范(英文版)
- GB50217-2007電力工程電纜設計規范(英文版)
- GB 50603-2010 鋼鐵企業總圖運輸設計規范(英文版)
- 工業文化研究(第2輯):紀念改革開放四十年——中國工業的大轉型
- GB50679-2011煉鐵機械設備安裝規范(英文版)
- GB 50403-2017 煉鋼機械設備工程安裝驗收規范
- GB50754-2012擠壓鋼管工程設計規范(英文版)
- 棉紡織工廠設計標準