4.9 Accumulator
4.9.1 The installation of accumulators shall comply with the following requirements:
1 The longitudinal and horizontal center lines shall be adjusted,and the measurement by plumb wire should be carried out,with the allowable deviation of 10.0mm.
2 The elevation shall be adjusted,and the measurement by optical instrument or ruler should be carried out,with the allowable deviation of±10.0mm.
3 The levelness or verticality shall be adjusted,and the measurement by leveler or suspension wire should be carried out,with the allowable deviation of 0.1/1000 for weight loaded accumulator and 1.0/1000 for other accumulators except weight loaded accumulator.The anchor bolts shall be tightened.
4.9.2 For accumulator installation,it is forbidden to open its vent cap,screw the safe valves,adjust the screws or change the ex-factory setting values.
- GB 50227-2017 并聯電容器裝置設計規范
- GB/T 50943-2015 海岸軟土地基堤壩工程技術規范
- GB 50349-2015 氣田集輸設計規范
- 真空電子器件生產線設備安裝技術標準
- GB/T 51257-2017 液化天然氣低溫管道設計規范
- GB50542-2009石油化工廠區管線綜合技術規范(英文版)
- GB 51134-2015 煤礦瓦斯發電工程設計規范
- GB 51176-2016 干混砂漿生產線設計規范
- GB 51162-2016 重型結構和設備整體提升技術規范
- GB 51156-2015 液化天然氣接收站工程設計規范
- DL/T 5505-2015 電力應急通信設計技術規程
- GB 51335-2018 聲屏障結構技術標準
- DL/T5210.4-2009電力建設施工質量驗收及評價規程第4部分:熱工儀表及控制裝置(英文版)
- GB50830-2013冶金礦山采礦設計規范(英文版)
- GB50754-2012擠壓鋼管工程設計規范(英文版)