4 Equipment Installation
4.1 General Requirements
4.1.1 The equipment completely assembled and adjusted in the factory should not be disassembled at site but installed as a whole.
4.1.2 As for the equipment which is supplied in the form of parts and elements,their cleaning and assembly at site shall comply with the requirements of the design technical document or the current national standard General Code for Construction and Acceptance of Mechanical Equipment Installation Engineering(GB 50231).
4.1.3 The connection of equipment and pipes shall not be carried out by brute force.After completion of connection,it is required to recheck whether the installation accuracy of the equipment meets the requirement.
推薦閱讀
- GB50526-2010公共廣播系統工程技術規范(英文版)
- GB51005-2014水泥工廠余熱發電工程施工與質量驗收規范(英文版)
- GB 50227-2017 并聯電容器裝置設計規范
- GB/T 51216-2017 移動通信基站工程節能技術標準
- GB 50469-2016 橡膠工廠環境保護設計規范
- 濕陷性土起始壓力測試規程
- GB50060-20083~110kV高壓配電裝置設計規范(英文版)
- GB50548-2010330kV-750kV架空輸電線路勘測規范(英文版)
- GB 51205-2016 精對苯二甲酸工廠設計規范
- GB 50603-2010 鋼鐵企業總圖運輸設計規范(英文版)
- Rhinoceros三維產品建模及后期處理
- VRP11虛擬現實編輯器標準教程
- DL/T5161.11-2002電氣裝置安裝工程質量檢驗及評定規程第11部分:電梯電氣裝置施工質量檢驗(英文版)
- 核電廠建構筑物維護及可靠性鑒定標準
- DL/T5161.13-2002電氣裝置安裝工程質量檢驗及評定規程第13部分:電力變流設備施工質量檢驗(英文版)