6 Protective Iron Parts and Operating Platform of Coke Oven

6.1 General Requirement

6.1.1 For the installation of coke oven body equipment,two construction technologies of building before installation of buckstays(hearafter referred to as Class A)and installing buckstays before building(hearafter referred to as Class B)may be adopted.

6.1.2 Before the installation of equipment,the measuring result of the previous working procedure is subjected to the check of actual measurement,simultaneously,the longitidinal and lateral center lines of coke oven bank,the center line of the side coking chamber,the installation datum lines of front lines on machine and coke sides and the center line of flue shall be set,and the perpetual central target and datum mark shall be embedded(Figure 6.1.2).

img

Figure 6.1.2 Datum line of coke oven

1-Center line of flue;2-Control line of oven length;3-Longitidinal center line of coke oven;4-Center line of side coking chamber;5-Lateral center line of coke oven

主站蜘蛛池模板: 兴和县| 衢州市| 凤翔县| 陈巴尔虎旗| 红河县| 永年县| 泰顺县| 凉城县| 长治县| 乌鲁木齐市| 叶城县| 安国市| 赫章县| 牟定县| 新兴县| 霞浦县| 锡林浩特市| 方正县| 丰顺县| 宝应县| 五台县| 察哈| 旺苍县| 宜春市| 称多县| 永新县| 盈江县| 绥滨县| 建始县| 哈密市| 正蓝旗| 托克托县| 伊通| 万全县| 金寨县| 平舆县| 兴宁市| 类乌齐县| 奉贤区| 菏泽市| 石泉县|