5.3 Installation of Reversible Device
5.3.1 Port frames should be installed after being assembled on the ground.
5.3.2 The welding of port frame beam and landing leg shall be performed after the acceptance of the elevation of landing leg top surface.
5.3.3 The installation of reversible device shall be performed after the qualified installation of port frames.
5.3.4 During the installation of reversible device,point of intersection of the center line of front and back wheel rails of walking structure and the center line of rail gauge is used as center of rotation,and center mark is indicated on the port frames.
5.3.5 Before the installation of reversible device,the large bearing sealing cap shall be disassembled to check whether rust,moisture and dirt exist inside the reversible device or not,and insufficient lubricating grease is added in accordance with grades specified by design documents.
5.3.6 The welding of rotation rail shall meet the requirements of design documents.After welding,welds shall be polished smoothly,and surface inspection shall be performed until it is qualified.
5.3.7 The installation of rotation rail shall be checked by extracting more than 8 equal diversion points on the circumference,and shall be in compliance with the following requirements:
1 Rail radius is adjusted,and allowable deviation shall be±4.0mm;
2 The elevation of each point on the top surface of rail is adjusted,and allowable deviation shall be±5.0mm;
3 The radius of centering supporting roll rail is adjusted,and allowable deviation shall be±4.0mm;
4 The radius of rotation pin gear is adjusted,and allowable deviation shall be±3.0mm;
5 Gap between the roller of centering roll and rail is adjusted,and allowable deviation shall be±1.0mm.
5.3.8 The installation of rotation balancers shall be in compliance with the following requirements:
1 The levelness of upper surface in longitudinal and lateral directions is adjusted,and allowable deviation shall be 1/1000 of side length;
2 Side lengths of a square formed by the four rotation balancers,and allowable deviation shall be±2.0mm;
3 Diagonal difference of the square formed by the four rotation balancers,and allowable deviation shall be 4.0mm.
- 城市地下空間規劃標準
- 電力調度數據網絡工程設計規程
- GB 50222-2017 建筑內部裝修設計防火規范
- GB/T50609-2010石油化工工廠信息系統設計規范(英文版)
- GB50580-2010連鑄工程設計規范(英文版)
- 換流站接地極設計文件內容深度規定
- 汽車故障診斷技巧與禁忌速查手冊
- 平板玻璃工廠節能設計標準
- GB50830-2013冶金礦山采礦設計規范(英文版)
- DL/T5161.11-2002電氣裝置安裝工程質量檢驗及評定規程第11部分:電梯電氣裝置施工質量檢驗(英文版)
- GB50397-2007冶金電氣設備工程安裝驗收規范(英文版)
- GB/T 50451-2017 煤礦井下排水泵站及排水管路設計規范
- GB 50390-2017 焦化機械設備安裝驗收規范
- DL/T5161.13-2002電氣裝置安裝工程質量檢驗及評定規程第13部分:電力變流設備施工質量檢驗(英文版)
- GB/T 51242-2017 同步數字體系(SDH)光纖傳輸系統工程設計規范