5.2 Optical Cable Route Selection
5.2.1 The lines should go from the bridge,when the optical cable routing goes across the river and a permanent solid bridge may be available for laying the lines nearby.Suitable places shall be chosen to deploy underwater cables whilst considering the main routing direction,to ensure the routing will not deviate too far.However,for complex and broad rivers or large rivers with busy shipping business,top priority shall be ensuring safety of the underwater routes,and partial deviation can be an option.
5.2.2 To ensure security as top priority,directional drilling or aerial laying methods may be used to lay optical cable lines across the river.
5.2.3 When optical cable lines come across a reservoir,optical cable lines shall go through the upstream of the reservoir and the laying height along the reservoir shall exceed the highest water storage level.
- GB 51287-2018 煤炭工業露天礦土地復墾工程設計標準
- GB 51245-2017 工業建筑節能設計統一標準
- 老年人智能技術應用入門
- DL/T5161.2-2002電氣裝置安裝工程質量檢驗及評定規程第2部分:高壓電器施工質量檢驗(英文版)
- GB50172-2012電氣裝置安裝工程蓄電池施工及驗收規范(英文版)
- DL/T 5546-2018 自然通風冷卻塔防腐設計導則
- YD/T 5131-2005 移動通信工程鋼塔桅結構設計規范(英文版)
- GB/T51050-2014鋼鐵企業能源計量和監測工程技術規范(英文版)
- GB/T 50643-2018 橡膠工廠職業安全衛生設計標準
- GB 51237-2017 火工品試驗室工程技術規范
- GB/T 51243-2017 物聯網應用支撐平臺工程技術標準
- 電子CAD技術項目化教程
- DL/T 5160-2015 電力工程巖土描述技術規程
- GB 51156-2015 液化天然氣接收站工程設計規范
- GB 51303-2018 船廠工業地坪設計標準