1 General Provisions

1.0.1 This code is formulated to assure the quality of and provide guidance and norms for the acceptance of photovoltaic power projects.

1.0.2 This code is applicable to the acceptance of new,modified and expanded ground and rooftop photovoltaic power projects connected to power grid with an rated voltage of 380V or above,it is not applicable to BIPV(Building Integrated Photovoltaic)and household PV projects.

1.0.3 Photovoltaic power projects shall be subjected to comprehensive acceptance check that is divided into four stages including Unit Project,project Start-up,Commissioning and Transfer to Production,and project completion.

1.0.4 Appropriate acceptance organization shall be established as per requirement for each stage acceptance,and a leading unit shall be determined for such an organization.

1.0.5 Besides this code,the acceptance of photovoltaic power projects shall comply with other current national standards.