2 Terms
2.0.1 Waste heat recovery(WHR)
The system utilizes the recoverable thermal energy exhausted in production process on the basis of environmental temperature.
2.0.2 Waste heat power generation(WHG)
To generate power by using waste heat discharged in cement production process.
2.0.3 Air quenching cooler boiler(AQC boiler)
The heat-exchange device to produce hot water,steam and other working mediums by utilizing waste heat of exhaust gas discharged from kiln head clinker cooler,AQC boiler for short.
2.0.4 Suspend preheater boiler(SP boiler)
The heat-exchange device to produce hot water,steam and other working mediums by utilizing waste heat of exhaust gas discharged from kiln tail preheater,SP or PH boiler for short.
2.0.5 Bypass boiler(BP boiler)
The heat-exchange device to produce hot water,steam and other working mediums by utilizing waste heat of exhaust gas discharged from kiln tail bypass,BP boiler for short.
2.0.6 Combined heat and power
Waste heat power generation may also supply heating to externality by hot water or steam at the same time of the production of electric energy.
2.0.7 Main building
Combined building equipped with steam turbine generator unit and the corresponding workshops.
2.0.8 Flasher
The container,which can enable the hot water at certain temperature and pressure to turn into the saturated steam under certain pressure because of the pressure decreasing.
2.0.9 Disconnection
The process of disconnecting the operation between the waste heat boiler and cement production line.
2.0.10 Percentage of auxiliary power
Ratio between the service power consumption and the total generation of the waste heat power generation system.
3.0.1 Waste heat power generation shall utilize the waste heat,which not be used any more in cement production process.
3.0.2 Design principles of waste heat power generation engineering shall be in accordance with the following requirements:
1 Waste heat power generation engineering shall not affect the normal operation of the cement production;
2 Waste heat power generation engineering shall neither increase the clinker comparable comprehensive energy consumption nor decrease clinker production;
3 Waste heat power generation engineering should be implemented after completing thermal calibration or investigation for operation condition when cement production lines reached the designed capacity and in stable operation;
4 In the synchronous construction with the cement production line,parameters of exhaust gas may be determined on the basis parameters of cement process design and that of waste heat power generation system which has been put into operation and has similar conditions;
5 The capacity of related equipment in production line shall be checked when the waste heat power generation systems are added to the original cement production line.
3.0.3 Design specifications of waste heat power generation shall be in accordance with those specified in Table 3.0.3.
Table 3.0.3 Design specifications of waste heat power generation

3.0.4 The automation control level of waste heat power generation system shall not be lower than that of cement production line.The related technical parameters of waste heat power generation system shall communicate with that in the control system of the cement production line.
3.0.5 The fire protection design of waste heat power generation system shall meet the relevant requirements of the current national standard Code for design of fire protection for fossil fuel power plants and substations GB 50229.
- 產品首版制作
- GB50713-2011板帶精整工藝設計規范(英文版)
- DL/T 5544-2018 架空輸電線路錨桿基礎設計規程
- GB 51138-2015 尿素造粒塔工程施工及質量驗收規范
- GB/T 50770-2013 石油化工安全儀表系統設計規范(英文版)
- GB 51221-2017 城鎮污水處理廠工程施工規范
- GB/T 50934-2013 石油化工工程防滲技術規范(英文版)
- GB/T 50938-2013 石油化工鋼制低溫儲罐技術規范(英文版)
- GB 50426-2016 印染工廠設計規范
- 平板玻璃工廠節能設計標準
- DL 5068-2014 發電廠化學設計規范
- DL/T 5097-2014 火力發電廠貯灰場巖土工程勘測技術規程
- DL/T 5501-2015 凍土地區架空輸電線路基礎設計技術規程
- 建筑施工技術(中職)
- DL/T5161.13-2002電氣裝置安裝工程質量檢驗及評定規程第13部分:電力變流設備施工質量檢驗(英文版)