5.4 Pipeline Arrangement
5.4.1 The thermodynamic pipes may be laid in the same pipe gallery and on the same pipe rack with the cement process pipes;in case any conflict occurs to the comprehensive layout of pipeline,the treatment mode shall meet the relevant requirements of the current national standard Code for design of general plan of industrial enterprises GB 50187.
5.4.2 In case underground pipelines are arranged within range of pavement,the method of direct burial or trench laying shall be determined by technical and economic comparison.
5.4.3 Overhead pipeline shall be arranged in accordance with the following requirements:
1 It shall use buildings(or structures)of cement production lines;
2 It shall not impede traffic,maintenance,natural lighting and natural ventilation of buildings,and shall ensure neat appearance;
3 Overhead lines should be arranged at corresponding position of underground pipelines.
5.4.4 The horizontal clear distance of underground pipelines,horizontal clear distance among underground pipelines,overhead pipelines and buildings(or structures),and vertical clear distance among underground pipelines and between underground pipelines and the intersections of railways and roads shall be determined by the engineering geology,framework foundation form,inspection shaft structure,burial depth of pipelines,pipe diameter,media inside pipes and other factors,and the minimum clear distances shall meet the relevant requirements of the current national standard Code for design of cement plant GB 50295.
5.4.5 Comprehensive layout of pipelines in renovation and extension projects shall not impede the normal use of existing pipelines.The distance among underground pipelines shall meet the relevant requirements of the current national standard Code for design of cement plant GB 50295.
- DL/T 5044-2014 電力工程直流電源系統(tǒng)設(shè)計技術(shù)規(guī)程
- 中文版Rhino 5.0完全自學教程(培訓教材版)
- 設(shè)計系統(tǒng)發(fā)展研究
- GB 51145-2015 煤礦電氣設(shè)備安裝工程施工與驗收規(guī)范
- GB/T 51216-2017 移動通信基站工程節(jié)能技術(shù)標準
- 真空電子器件生產(chǎn)線設(shè)備安裝技術(shù)標準
- 強夯地基技術(shù)規(guī)程
- 滌綸工廠設(shè)計標準
- DL/T 5001-2014 火力發(fā)電廠工程測量技術(shù)規(guī)程
- GB 50169-2016 電氣裝置安裝工程 接地裝置施工及驗收規(guī)范
- GB50071-2014小型水力發(fā)電站設(shè)計規(guī)范(英文版)
- GB50679-2011煉鐵機械設(shè)備安裝規(guī)范(英文版)
- GB 50588-2017 水泥工廠余熱發(fā)電設(shè)計標準
- DL/T 5097-2014 火力發(fā)電廠貯灰場巖土工程勘測技術(shù)規(guī)程
- 建筑施工技術(shù)(中職)