4.3 Base Line and Base Point for Equipment Installation
4.3.1 Before the equipment eretion,the base line and base point shall be set for its installation and shall comply with the following requirements:
1 The arrangement of base lines and base points shall be prepared in accordance with the construction drawing and surveying control network,and then the positions of the central guide board and base points shall be determined.
2 The center marks and base points shall be arranged according to the arrangement drawing.
3 The surveying assignment shall be transmitted to the surveyor.
4 The surveying personnel shall carry out surveying,shaft plumbing and setting out and finally accomplish the surveying works.
5 The surveyor shall submit the report of surveying results to related superiors and also hand over the base lines and base points to the installation construction personnel at site.
- 焊接技能實訓
- DL/T 5544-2018 架空輸電線路錨桿基礎設計規程
- GB/T 51331-2018 煤焦化焦油加工工程設計標準
- GB 51220-2017 生活垃圾衛生填埋場封場技術規范
- GB/T 51332-2018 含硝基苯類化合物廢水處理設施工程技術標準
- GB/T 50761-2018 石油化工鋼制設備抗震設計標準
- 標準貫入試驗規程
- GB/T 50436-2017 線材軋鋼工程設計標準
- DL/T 5505-2015 電力應急通信設計技術規程
- SH/T 3405-2012 石油化工鋼管尺寸系列(英文版)
- GB50679-2011煉鐵機械設備安裝規范(英文版)
- GB 50414-2018 鋼鐵冶金企業設計防火標準
- GB 51208-2016 人工制氣廠站設計規范
- GB/T 50398-2018 無縫鋼管工程設計標準
- GB/T 50312-2016 綜合布線系統工程驗收規范