3.4 Quantity of Pulverized Coal Injection
3.4.1 PCI quantity shall be determined according to conditions such as raw materials,fuels,air temperature,oxygen enrichment,BF top pressure,and blast humidity.PCI quantity under different smelting conditions should be in accordance with those specified in Table 3.4.1,and shall comply with the following requirements:
1 If blast is of natural humidity and the hot air temperature is between 1050°C-1100°C,the lower limit in Table 3.4.1 shall be used.
2 The upper limit in Table 3.4.1 may be used under the following conditions:high coke strength,small slag quantity,dehumidified blast,hot air temperature of 1200°C-1250°C,and BF top pressure over 0.20MPa.
Table 3.4.1 PCI quantity under different smelting conditions

3.4.2 If the smelting conditions exceed the specified range in Article 3.4.1 of this Standard,PCI quantity can be determined through calculating the theoretical combustion temperature before tuyere.The theoretical combustion temperature before tuyere should be 2100°C±50°C.
3.4.3 Equipment capacity of PCI system shall be surplus to the PCI quantity for BF,but the maximum PCI quantity should not be larger than 250kg/tHM.
- GB50950-2013光纜廠生產設備安裝工程施工及質量驗收規范(英文版)
- GB 50227-2017 并聯電容器裝置設計規范
- GB 51289-2018 煤炭工業露天礦邊坡工程設計標準
- GB 50349-2015 氣田集輸設計規范
- 真空電子器件生產線設備安裝技術標準
- GB/T 51183-2016 農業溫室結構荷載規范
- GB 50471-2018 煤礦瓦斯抽采工程設計標準
- 濕陷性土起始壓力測試規程
- GB 50545-2010110kV~750kV架空輸電線路設計規范(英文版)
- GB 50169-2016 電氣裝置安裝工程 接地裝置施工及驗收規范
- GB50439-2015煉鋼工程設計規范(英文版)
- GB/T 51200-2016 高壓直流換流站設計規范
- GB50071-2014小型水力發電站設計規范(英文版)
- GB/T 50459-2017 油氣輸送管道跨越工程設計標準
- DL/T 866-2015 電流互感器和電壓互感器選擇及計算規程