3 Equipment Foundation,Anchor Bolts and Shim Plates
3.1 Equipment Foundation
3.1.1 Before being installed,equipment foundation shall be subjected to handover acceptance,and one not subjected to handover acceptance shall not be installed.
3.1.2 The handover acceptance of equipment foundation shall be in compliance with the following requirements:
1 Basic acceptance material shall be complete;
2 The strength grades of foundation concrete shall meet the requirements of design documents,and acceptance material and records shall be reserved;
3 The position and size of foundation shall meet the requirements of Code for Construction and Acceptance of Mechanical Equipment Installation Work GB 50231 as national standard;
4 Formwork on the surface of foundation,anchor bolt fixing frame,etc.shall be removed,and laitance,oil stain,broken stone,mud,accumulated water,etc.on the surface of foundation and in anchor bolt holes shall be removed;
5 Built-in anchor bolts shall have no damage,threads shall be cleaned and coated with grease and have the protective measures.
3.1.3 Design documents and relevant specifications and provisions shall include equipment foundation subjected to settlement observation,settlement observation records and settlement observation points shall be handed over,and settlement observation shall be proceeded to perform in the process of equipment installation.
- DL/T 5526-2017 換流站噪聲控制設計規程
- YS/T 5225-2016土工試驗規程
- GB/T 50770-2013 石油化工安全儀表系統設計規范(英文版)
- GB/T 51331-2018 煤焦化焦油加工工程設計標準
- GB 51221-2017 城鎮污水處理廠工程施工規范
- DL/T 5512-2016 火力發電廠熱工檢測及儀表設計規程
- GB50217-2007電力工程電纜設計規范(英文版)
- DL/T5231-2010±800kV及以下直流輸電接地極施工及驗收規程(英文版)
- 鐵路罐車清洗設施設計標準
- DL/T 5543-2018 特高壓輸變電工程環境影響評價內容深度規定
- GB 50311-2016 綜合布線系統工程設計規范
- GB/T 51169-2016 煤炭工業礦井采掘設備配備標準
- GB50967-2014焦化機械設備安裝規范(英文版)
- GB 51247-2018 水工建筑物抗震設計標準
- GB/T 51172-2016 在役油氣管道工程檢測技術規范