10.6 Installation of Cleaning Device of Oven Port Frames
10.6.1 Before the installation of cleaning device of oven port frames,the center mark which is authorized is set on the platform beam.
10.6.2 The adjusting shim plate shall be accurate in position,and shall be cushioned compactly.
10.6.3 S type slideway shall be installed after the installation of port extractor main body.During installation,S type slideway should be subjected to preliminary orientation,and fixed after the positions of cleaning device of oven port frames are determined during test running.
10.6.4 Welding quality shall meet the requirements of design documents and Code for Construction and Acceptance of Field equipment,Industrial Pipe Welding Work GB 50683 as current national standard,namely the check grade of the appearance quality of welds of site equipment is gradeⅢ.
10.6.5 The installation of rails of cleaning device of oven port frames shall be in compliance with the following requirements:
1 The elevation of rails of cleaning device is adjusted,and allowable deviation shall be±5.0mm;
2 Height difference of any two points in full stroke is adjusted,and allowable deviation shall be 2.0mm;
3 Height difference on the same cross section on left and right rails is adjusted,and allowable deviation shall be 2.0mm;
4 Space between upper and lower rails on the same side is adjusted,and allowable deviation shall be
5 The center distance of left and right rails and cleaning device of oven port is adjusted,and allowable deviation shall be
6 The distance of centers of rails and coke pushing center is adjusted,and allowable deviation shall be±2.0mm.
10.6.6 The installation of cleaning device of oven port frames shall be in compliance with the following requirements:
1 The perpendicularity of cleaning head of oven port frames along the width direction of coking chamber at operating position is adjusted,and allowable deviation shall be 8.0mm;
2 The perpendicularity of cleaning head of oven port frames along the length direction of coking chamber at operating position is adjusted,and allowable deviation shall be 10.0mm;
3 The deviation of the center of operating position of cleaning head and the center of coke pushing ram is adjusted,and allowable deviation shall be±5.0mm.
- GB 51276-2018 煤炭企業總圖運輸設計標準
- 工業企業技術改造升級投資指南:指南 解讀 案例(2023年版)
- GB 51326-2018 鈦冶煉廠工藝設計標準
- SH3011-2011石油化工工藝裝置布置設計規范(英文版)
- DL/T5161.3-2002電氣裝置安裝工程質量檢驗及評定規程第3部分:電力變壓器、油浸電抗器、互感器施工質量檢驗(英文版)
- DL/T 5001-2014 火力發電廠工程測量技術規程
- GB50764-2012電廠動力管道設計規范(英文版)
- GB/T 51175-2016 煉油裝置火焰加熱爐工程技術規范
- GB 51184-2016 礦山提升井塔設計規范
- GB50402-2007燒結機械設備工程安裝驗收規范(英文版)
- GB 50426-2016 印染工廠設計規范
- GB 50360-2016 水煤漿工程設計規范
- DL/T 5516-2016 火力發電廠集中控制室及電子設備間布置設計規程
- 工程建設標準體系(農業工程部分)
- GB/T 50387-2017 冶金機械液壓、潤滑和氣動設備工程安裝驗收規范