7.6 Installation of Stack Gate Valve

7.6.1 Flue shutter shall be installed completely before oven dry-off.

7.6.2 Flue shutter shall be preassembled before installation,and the allowable deviation of gap between turning plate and flue shall be±5.0mm.

7.6.3 During installation,flue shutter shall keep vertical and flexible rotation,sealing cover plate shall be tight,the on/off position and on/off direction of index dial shall meet the requirements of design documents.

7.6.4 The installation of the stack gate valve shall be in compliance with the following requirements:

1 The center of the stack gate valve is adjusted,and allowable deviation shall be 10.0mm;

2 The elevation the stack gate valve is adjusted,and allowable deviation shall be±10.0mm;

3 The levelness of beam on the top of the stack gate valve is adjusted,and allowable deviation shall be 1/1000 of beam length.