4 Equipment and Material
4.1 Equipment
4.1.1 Equipment approach plan shall be formulated in accordance with equipment delivery schedule and construction schedule for organization.
4.1.2 The open-box inspection of equipment shall keep records and shall be in compliance with the following requirements:
1 Check box number,box number and packaging condition,and package appearance shall not have obvious damage;
2 Equipment name,model and specification shall meet the requirements of design documents;
3 Check the number of appearance quality of equipment and parts,loss and damage to parts shall be avoided,and damage,rust and deformation on surface shall also be avoided;
4 Random technical documents,special tools and spare parts for equipment boxing shall be complete;
5 Equipment shall include conformity certificates,and imported equipment shall include commercial inspection conformity certificates.
4.1.3 After equipment box is opened,equipment and parts and special tools shall be kept properly,and deformation,damage,rust or loss shall be avoided.
4.1.4 During equipment conveying,the hoisting point shall be positioned at the marking position or design hoisting point of equipment and packaging box,and during conveying,protective measures shall be provided to avoid equipment damage.
- DL/T 5044-2014 電力工程直流電源系統設計技術規程
- GB 50388-2016 煤礦井下機車車輛運輸信號設計規范
- GB51005-2014水泥工廠余熱發電工程施工與質量驗收規范(英文版)
- GB/T 51338-2018 分布式電源并網工程調試與驗收標準
- GB/T51167-2016海底光纜工程驗收規范(英文版)
- GB 51209-2016 發光二極管工廠設計規范
- GB50580-2010連鑄工程設計規范(英文版)
- DL/T 5156.1-2015 電力工程勘測制圖標準 第1部分:測量
- 換流站接地極設計文件內容深度規定
- 標準貫入試驗規程
- GB50468-2008焊管工藝設計規范(英文版)
- DL/T 5543-2018 特高壓輸變電工程環境影響評價內容深度規定
- DL 5068-2014 發電廠化學設計規范
- GB/T 51272-2018 煤炭工業智能化礦井設計標準
- GB/T 50417-2017 煤礦井下供配電設計規范