1 Scope
This Part in DL/T 5210 specifies the relevant requirements in the construction quality acceptance standard for instrumentation and control device("instrumentation and control",or"I&C"),and quality evaluation for individual project,individual unit and overall project.
This Part is applicable to the construction quality acceptance and engineering quality evaluation of I&C device for newly-built,extended and rebuilt thermal power generation projects with unit capacity 300MW-1000MW.The unit capacity construction quality acceptance and evaluation of I&C device for thermal power generation project with unit capacity under 300MW may comply with this Part by reference.
推薦閱讀
- GB/T 50537-2017 油氣田工程測量標(biāo)準(zhǔn)
- GB/T 51146-2015 硝化甘油生產(chǎn)廢水處理設(shè)施技術(shù)規(guī)范
- 高素質(zhì)應(yīng)用型工程技術(shù)人才培養(yǎng)理論與實踐探索
- GB 50243-2016 通風(fēng)與空調(diào)工程施工質(zhì)量驗收規(guī)范
- GB/T 51257-2017 液化天然氣低溫管道設(shè)計規(guī)范
- GB50542-2009石油化工廠區(qū)管線綜合技術(shù)規(guī)范(英文版)
- 微波集成組件生產(chǎn)工廠工藝設(shè)計標(biāo)準(zhǔn)
- GB 50426-2016 印染工廠設(shè)計規(guī)范
- GB/T 51025-2016 超大面積混凝土地面無縫施工技術(shù)規(guī)范
- GB 51135-2015 轉(zhuǎn)爐煤氣凈化及回收工程技術(shù)規(guī)范
- DL 5068-2014 發(fā)電廠化學(xué)設(shè)計規(guī)范
- 陽極焙燒爐用多功能機(jī)組安裝技術(shù)規(guī)程
- 工程建設(shè)標(biāo)準(zhǔn)體系(農(nóng)業(yè)工程部分)
- DL/T 5028.3-2015 電力工程制圖標(biāo)準(zhǔn) 第3部分:電氣、儀表與控制部分
- GB/T 51280-2018 工程泥沙設(shè)計標(biāo)準(zhǔn)