2.3 Splicing and Correction
2.3.1 The splicing of the material should adopt equal strength welding manner;when the attachment weld joint strength is less than the base metal strength,the reinforcement shall be done.
2.3.2 When field welding H-shaped steels,the spacing of the splicing weld joint of the flange plate and the splicing weld joint of the web plate shall not be less than 200mm.The splicing length of the flange plate shall not be less than 2 times of the plate width and shall not be less than 500mm.The splicing width of the web plate shall not be less than 300mm,the length shall not be less than 600mm,and the splicing weld joint spacing of the web plate should not be less than 200mm.
2.3.3 The measures to reduce welding deformation shall be taken when splicing materials,the plainness,offset and buckling shall meet the requirements of"The Code of Welding for Power Plant"(DL/T 869).
2.3.4 When heating carbon structural steels and low-alloy structural steels for correction,the heating temperature shall not exceed 900℃.The low-alloy structural steel shall be carried out with natural cooling after heating and correction.
2.3.5 The minimum curvature radius and maximum bending vector height for cold correcting and cold bending of steels shall be in accordance with those specified in Table 2.3.5.
Table 2.3.5 Minimum curvature fadius and maximum bending vector height for cold correcting and cold bending(mm)

Note:r refers to curvature radius;f refers to bending vector height;L refers to bending chord length;t refers to steel plate thickness;b refers to the leg width of the angle steel,channel steel and I-shaped steel;h refers to the height of the channel steel and I-shaped steel.
2.3.6 The allowable deviation of the steel that after correction shall be in accordance with those specified in Table 2.3.6.
Table 2.3.6 Allowable deviation of steel after correction(mm)

Note:Δ—allowable deviation of steel after correction.
- GB/T 50537-2017 油氣田工程測量標(biāo)準(zhǔn)
- GB 51145-2015 煤礦電氣設(shè)備安裝工程施工與驗收規(guī)范
- GB 50428-2015 油田采出水處理設(shè)計規(guī)范
- GB/T50663-2011核電廠工程水文技術(shù)規(guī)范(英文版)
- 光伏支架結(jié)構(gòu)設(shè)計規(guī)程
- 石油化工廠際管道工程技術(shù)標(biāo)準(zhǔn)
- 水泥工廠環(huán)境保護(hù)設(shè)施設(shè)計標(biāo)準(zhǔn)
- DL/T 5508-2015 燃?xì)夥植际焦┠苷驹O(shè)計規(guī)范
- GB 51176-2016 干混砂漿生產(chǎn)線設(shè)計規(guī)范
- GB 51222-2017 城鎮(zhèn)內(nèi)澇防治技術(shù)規(guī)范
- GB 50545-2010110kV~750kV架空輸電線路設(shè)計規(guī)范(英文版)
- GB50427-2015高爐煉鐵工程設(shè)計規(guī)范(英文版)
- GB 51170-2016 航空工業(yè)工程設(shè)計規(guī)范
- GB 51171-2016 通信線路工程驗收規(guī)范
- GB50830-2013冶金礦山采礦設(shè)計規(guī)范(英文版)