5 Welding Work
5.1 General Requirements
5.1.1 This chapter is applicable to the quality acceptance of welding work for steel tower and mast structure during manufacture and installation.
5.1.2 The welding work of steel tower and mast structure may be divided to one or several inspection lots according to the corresponding division principles of inspection lots for the manufacture and installation work of steel tower and mast structure.
5.1.3 For carbon construction steel,the flaw detection of welding seam shall be carried out after the welding seam has cooled to the ambient temperature;and for low-alloy construction steel,the flaw detection of welding seam shall be carried out 24hrs later than the completion of welding.
5.1.4 After the completion of welding seam,the name of welder performing the welding seam shall be stamped on the welding seam and area specified in welding procedure by the steel seal of the welder.
5.1.5 The quality of welding seam on steel pole shall be in conformity with the design requirements.Girth butt-jointed welding seam of pipes shall take the form of full penetration welding joint and not be less than gradeⅡ.The quality of longitudinal butt-jointed welding seam should not be less than gradeⅡand the quantity of longitudinal welding seam shall not be more than two.
5.1.6 Where butt-jointed welding is conducted for main structure,the number of butt welding joints should not exceed one within one rod section or one tower layer.
- DL/T5161.10-2002電氣裝置安裝工程質量檢驗及評定規程第10部分:35kV及以下架空電力線路施工質量檢驗(英文版)
- GB50460-2015 油氣輸送管道跨越工程施工規范
- 高素質應用型工程技術人才培養理論與實踐探索
- DL/T 5546-2018 自然通風冷卻塔防腐設計導則
- GB/T 51216-2017 移動通信基站工程節能技術標準
- GB50542-2009石油化工廠區管線綜合技術規范(英文版)
- GB/T 51183-2016 農業溫室結構荷載規范
- GB 51006-2014 石油化工建(構)筑物結構荷載規范(英文版)
- 標準貫入試驗規程
- 換流站接地極設計文件內容深度規定
- 鄭州軌道交通機電設備運營需求標準
- SH/T 3096-2012 高硫原油加工裝置設備和管道設計選材導則 (英文版)
- GB 51170-2016 航空工業工程設計規范
- VRP11虛擬現實編輯器標準教程
- 鋰離子電池工廠設計標準