5.6 Test Run
5.6.1 Carry out not less than 5 times back-forth move for the rolling mill low-speed screw down device and high-speed screw down device.High-low limiting position shall be accurate.
Inspection method:observation,check test run record.
5.6.2 Not less than 0.5 hour no load run of the main drive motor;the motor drives the reducer for not less than 0.5 hour test run;The motor drives the reducer,gear seat for not less than 0.5 hour test run;The motor drives reducer,gear seat and rolling mill for at least not less than 2 hours test run at 25%,50%,75%,100% of rated speed respectively.The reversible rolling mill shall also need run forward and reverse not less than 1 hour individually according to the aforementioned four classes.When several rolling mills drove by one driving device,supposed to run the first rolling mill,then carry out the test run for the second one and the rest can be done in the same manner until the last one be finished.
Inspection method:observation,check test run record.
5.6.3 Run the roll changing device and other equipment forward and backward 5 to 10 times.The stop position shall meet the requirements of technical documents.
Inspection method:observation,check test run record.
- YS/T 5225-2016土工試驗規程
- 健康座椅
- GB/T 51338-2018 分布式電源并網工程調試與驗收標準
- 電力調度數據網絡工程設計規程
- GB 50428-2015 油田采出水處理設計規范
- DL/T 5546-2018 自然通風冷卻塔防腐設計導則
- GB50432-2007煉焦工藝設計規范(英文版)
- GB 51209-2016 發光二極管工廠設計規范
- GB/T51154-2015海底光纜工程設計規范(英文版)
- GB/T 51025-2016 超大面積混凝土地面無縫施工技術規范
- 鐵路罐車清洗設施設計標準
- 海上架空輸電線路設計技術規程
- GB50427-2015高爐煉鐵工程設計規范(英文版)
- SH/T 3096-2012 高硫原油加工裝置設備和管道設計選材導則 (英文版)
- GB 50403-2017 煉鋼機械設備工程安裝驗收規范