5 Project Management Departments and Facilities

5.1 Project Management Department

5.1.1 Project management enterprises shall establish project management departments during the enforcement of the construction management contract.

5.1.2 Organizational structures and business scales of project management departments shall be determined by contents and periods of services,categories and scales of projects,complexity of technology,engineering environment and other factors stipulated in the construction management contract.

5.1.3 Project management departments are composed of chief project management engineers,specialty project management engineers and site supervisors.Staff arrangement shall satisfy the requirement of project management.Positions of representatives of chief project management engineers and deputy chief project management engineers should be established when necessary.

5.1.4 Owners shall be informed the organizational structure,the staff composition and the appointment of chief project management engineers in writing by the project management enterprises before the contract agreed time.Adjustment of chief project management engineers shall be notified in writing to owners,and be given the consent of the owners;adjustment of specialty project management engineers shall be notified in writing to owners and contractors by chief the project management engineers.

5.1.5 Chief project management engineers in charge of survey and design shall have at least 10-year working experience of relevant professional background,and the requirement for specialty project management engineers is at least 5-year working experience.

5.1.6 Chief project management engineers in charge of construction and commissioning shall have at least 5-year engineering practice experience with at least 3-year practice experience on similar projects.

5.1.7 Project management departments shall implement duties in accordance with the responsibility and permission agreed in the construction management contract until completion of the contract.

5.1.8 Project management departments shall stipulate working procedures and management regulations that are appropriate to the management content.

5.1.9 The chief project management engineer shall not undertake the management work for two or more projects at the same time unless permitted by the owner.