6 Stage Acceptance
6.1 General Requirements
6.1.1 The stage acceptance shall include diversion (closure) acceptance, impounding acceptance, acceptance of turbine-generator startup and others requested by the presiding organisation according to the needs of the construction project.
6.1.2 The stage acceptance shall be chaired by the presiding organization or its entrusted organization for completion acceptance. The stage acceptance committee consists of representatives and relevant experts from the acceptance presiding organization, quality and safety supervision organization and operation and management organization. Officials from the local government and relevant departments may be invited if it is necessary.
The organizations involved in the project shall appoint representatives to attend the stage acceptance and sign on the appraisal report as the organizations being accepted.
6.1.3 When the construction is ready for the stage acceptance, the legal person shall submit an application (see Annex F for contents). The application shall be reviewed by the supervision and management organization and then reported to presiding organization who should give a decision for an agreement or a disagreement within 15 working days after it is received.
6.1.4 Stage acceptance shall include the following contents:
1 Examination of the appearance and quality of completed projects.
2 Examination of the construction situation.
3 Examination of uncompleted projects and implementation of main technologies as well as the construction conditions.
4 Examination of operation conditions for projects planned to be commissioned.
5 Examination of remaining problems and treatment situation of the previous acceptances.
6 Assessment of the quality of completed works.
7 Tackling suggestions for problems found in the acceptance.
8 Discussion and passing of the appraisal report for stage acceptance.
6.1.5 Stage acceptance shall include the following procedures:
1 An on-site investigation should be conducted on the construction situation and relevant data should be checked and read.
2 Meetings should be held for making:
1)Announce the list of stage acceptance committee members.
2)Listen to the work reports by the organizations involved in the project.
3)Discuss and pass the appraisal report for stage acceptance.
4)Ask representatives from the acceptance committee and organizations to sign the appraisal report.
6.1.6 Annex G shows the appraisal report format for stage acceptances. The appraisal report shall be sent to relevant institutions by the presiding organizations, within 20 working days after getting its approval.
- 廣東抽水蓄能電站工程地質(zhì)創(chuàng)新與研究
- 河湖保護(hù)與修復(fù)的理論與實踐
- 龍灘機(jī)電及金屬結(jié)構(gòu)設(shè)計與研究
- 大孔隙介質(zhì)滲流特性研究
- 山洪災(zāi)害預(yù)警預(yù)報技術(shù)
- 水文地質(zhì)勘察技術(shù)
- 防汛抗旱與應(yīng)急管理實務(wù)
- 中國混凝土面板堆石壩30年:引進(jìn)·發(fā)展·創(chuàng)新·超越
- 河流泥沙動力學(xué)(第二版)
- 水工鋼筋混凝土結(jié)構(gòu)學(xué)(第5版)
- 全國中小河流治理重點縣綜合整治和水系連通:試點項目典型項目區(qū)實施方案選編
- 水利閘站工程監(jiān)理實施細(xì)則
- 水利水電施工(2017年第6輯)
- 江西省中小型水利水電工程單元工程施工質(zhì)量驗收評定表(試行)(第五冊):其他工程
- 水資源定價理論與方法研究